Searching over 5,500,000 cases.


searching
Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.

TWB Architects, Inc. v. Braxton LLC

Court of Appeals of Tennessee, Nashville

October 30, 2014

TWB ARCHITECTS, INC.
v.
THE BRAXTON, LLC, ET AL.

Session July 29, 2014

Appeal from the Chancery Court for Cheatham County No. 14181 Robert E. Burch, Judge

Donald Capparella, Nashville, Tennessee, for the appellant, TWB Architects, Inc.

William R. O'Bryan, Jr. and Kevin C. Baltz, Nashville, Tennessee, for the appellees, The Braxton, LLC and Fidelity and Deposit Company of Maryland.

Andy D. Bennett, J., delivered the opinion of the court, in which Frank G. Clement, Jr., P.J., M.S., and Richard H. Dinkins, J., joined.

OPINION

ANDY D. BENNETT, JUDGE

Facts and Procedural History

On February 17, 2005, Progress Capital Partners, LLC ("Progress Capital") and TWB Architects, Inc. ("TWB") entered into a contract entitled "AIA[1] Document B151-1997, Abbreviated Standard Form of Agreement Between Owner and Architect" (hereinafter "Architect Agreement") for TWB to provide architectural and design services for a mid-rise condominium project in Ashland City known as "The Braxton." The Architect Agreement was signed by John Rankin, Chief Manager of Progress Capital, and by Timothy Burrow, President of TWB. The fifteen-page Architect Agreement outlined, inter alia, the architect's responsibilities, the scope of the services, the owner's responsibilities, and the terms of compensation. Pursuant to the Architect Agreement, TWB would be paid a fee of two percent of construction costs or, if the project was not constructed, TWB would be paid by the hour, plus expenses.

On February 9, 2006, The Braxton, LLC was formed with Mr. Rankin as its Chief Manager. On February 16, 2006, Mr. Burrow and The Braxton, LLC entered into a contract entitled "Agreement for Sale of Residence the Braxton Condominiums at Harpeth Shoals" (hereinafter "Purchase Agreement"). In the Purchase Agreement, The Braxton, LLC agreed to sell Mr. Burrow Penthouse P6 in the Braxton Condominiums for "$0 in consideration of design fees owed in the Contract for architectural design between Progress Capital Partners, LLC and TWB Architects, Inc. dated 2/17/05."[2] The Purchase Agreement was signed by Mr. Burrow individually and by Mr. Rankin on behalf of The Braxton, LLC. Construction began on the project in the summer of 2006, and the condominiums were built according to the architectural plans drawn by TWB. As construction progressed, Mr. Burrow invested $39, 343.84 of his own money in upgrades to Penthouse P6.

On January 8, 2007, Charles Elcan became a member of The Braxton, LLC. On September 26, 2008, Mr. Rankin surrendered his membership interest in The Braxton, LLC leaving Mr. Elcan as the only member. On October 28, 2008, Mr. Rankin filed a voluntary petition for Chapter 7 bankruptcy. Thereafter, Mr. Burrow requested that The Braxton, LLC convey Penthouse P6 to him. The Braxton, LLC filed a Notice of Completion of the project on December 5, 2008 stating that the "[d]ate of completion of the improvement" was "October 21, 2008." In December 2008, Mr. Burrow moved into the penthouse.

In early 2009, TWB learned that the penthouse was encumbered by a security interest held by Bank of America and that The Braxton, LLC was unable to transfer it to Mr. Burrow free and clear of the encumbrance. On May 8, 2009, the Chancery Court of Davidson County gave a receiver the right of possession to every condominium at the Braxton. Mr. Burrow moved out of the penthouse in late 2009.

It is undisputed that The Braxton, LLC never deeded the penthouse condominium to Mr. Burrow or paid anything to TWB for its architectural services. On February 26, 2009, TWB filed a mechanic's lien in the Register of Deeds Office for Cheatham County. The Notice of Lien Claim stated:

Timothy W. Burrow, being first duly sworn, says that TWB Architects, Inc., the Lien Claimant, performed certain work or labor in furtherance of improvements to the real property herein described, in pursuance of certain contract with Owners, which owes Lien Claimant $882, 526.14 (which is over and above all legal setoffs), for which amount Lien Claimant claims a lien under T.C.A. §§ 66-11-101, et seq. on the real property.

On March 11, 2009, TWB filed a Complaint for Foreclosure of Mechanic's Lien against The Braxton, LLC.[3] The complaint alleged a single cause of action to enforce its mechanic's lien and sought to "be awarded a judgment for the amount stated in its Notice of Lien Claim . . . ." On May 6, 2009, The Braxton, LLC filed a counterclaim and argued that the Purchase Agreement served as a novation of the Architect Agreement, extinguishing TWB's right to assert any claims or remedies arising under the Architect Agreement.

The Braxton, LLC filed a motion for summary judgment on January 4, 2013, asserting that the Purchase Agreement replaced or extinguished the Architect Agreement.[4] On April 19, 2013, TWB filed its own motion for summary judgment. TWB argued that it earned the two percent fee contemplated in the Architect Agreement because The Braxton, LLC used the architectural plans designed by TWB and failed to pay TWB as required under the contract.[5]

On July 11, 2013, the trial court held a hearing on the motion, and by order entered November 18, 2014, the trial court granted The Braxton, LLC's motion for summary judgment. The court made the following pertinent findings:

(3) At the time of the Architect Agreement and the Purchase Agreement, [Progress Capital], The Braxton and John Rankin were in privity with and alter-egos of one another. Similarly, TWB and Mr. Burrow were ...

Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.